Step 7: On the Generating Database Scripts for Migration screen, the progress of generation of database scripts that are required for migration is displayed. If you have opted to back up the database in step 2, then a backup of the selected projects is created in the QFD database.

After the project backup completes, click Next.
The following confirmation message appears:

...

Step 9: On the Finalizing Migration screen, the project migration progress is displayed.

After the project migration completes, click Next.

...

Info

You must manually check in the migrated project folders present in the version control system that you use.

Post Migration Steps

...

After migrating the

...

projects, in the Qualitia Automation Studio 8.0.x, you need to

...

do the following:

  • Recreate the missing artifacts (Test case and tasks) in Qualitia Automation Studio 8.0.x. While that you skipped during the project migration, if you have added .

  • Recreate the custom actions, which were replaced by a dummy custom action, you need to develop the custom action.

  • You need to recreate Recreate the offline suites. For more information, refer to Offline Package .