Points to Know

  • If you are using Qualitia v7.3.0 or above, there is no need to migrate projects.

  • The following are two ways for migrating the projects:

    • Using Project Migration Utility: Qualitia provides a Utility to migrate multiple projects in a single instance.

    • Using Qualitia Client: From Qualitia v7.3.0, if you select a non-migrated project, an error message is displayed in Qualitia that prompts you to migrate the selected project only. Upon clicking Migrate Now on this message, Qualitia guides you for migration of the selected project only.

  • In each screen of the migration process, you have an option to go to the previous screen or cancel the migration process at any time.

  • Any user having database and version control tool credentials can run the Project Migration Utility.

Recommendations for Project Migration

  • Latest versions of test cases and tasks must be available in the Project path

  • The Qualitia database is accessible

  • Migration process might take extended time based on the project size. Therefore, plan to initiate migration accordingly.

  • Perform the project migration on a machine with at least below configurations for better turn-around time.

    • RAM - 16 GB

    • Quad-Core Processor

    • Free Disk Space - 5GB

Also, the migration process completes faster if other programs are not running on the machine.

Launching the Project Migration Utility

To launch the Project Migration Utility:

  1. Open the Qualitia Installable.

  2. Under the QualitiaProjectMigrationUtility folder, unzip the QualitiaProjectMigrationUtility.exe through 7-Zip file archiver only.

  3. Execute the QualitiaProjectMigrationUtility.exe

Migrating Projects

Info

Project Migration using Qualitia Client

If you are migrating a single project from a Qualitia client, there is no need to enter database or version control details. If some project artifacts do not match with version control, Qualitia directly opens the details of artifacts missing screen, as described in step 5.

Else, it directly displays the Project Health Checkup screen as described in step 6..

...

Click Finish to exit the Project Migration Utility.

...

Post Migration Considerations

After migrating a project, you must perform the following operations:

...