The Project artefacts created in Qualitia for desktop must be compatible with Qualitia Automation Studio v8.0.0. Therefore, Qualitia has provided a QFD Project migration Utility to migrate the QFD projects to Qualitia Automation Studio v8.0.0.

Recommendations for Project Migration

  • Ensure that you must have access to:

    • QFD database

    • Version Control, if it is integrated with QFD project artifacts

    • QAS 8.0.0 database

  • The project path must be updated with the latest versions of test cases and tasks.

  • The migration process might take an extended time based on the project size. Therefore, plan to initiate migration accordingly.

  • Perform the project migration on a machine with at least below configurations for better turn-around time.

    • RAM - 16 GB

    • Quad-Core Processor

    • Free Disk Space - 5GB

Also, the migration process completes faster if other programs are not running on the machine.

Launching the Project Migration Utility

To launch the Project Migration Utility:

  1. Open the Qualitia Installable.

  2. Under the QualitiaProjectMigrationUtility folder, extract the QualitiaProjectMigrationUtility.exe through 7-Zip file archiver only.

  3. Execute the QualitiaProjectMigrationUtility.exe

Performing the Project Migration Process

The Utility performs the project migration in the following three phases:

...

Click Finish to exit the project migration utility.

Post Migration Considerations

  • While the project migration, if you have skipped any missing artifact, you need to recreate them in Qualitia Automation Studio 8.0.0.

  • While the project migration, if you have added a dummy custom action VBS file, you need to do the required coding in the migrated VBS file.

  • You need to recreate offline suites using the offline package. For more information, refer to Offline Package

...